Filling the circuits

When the instrument holder manifold is installed in a geothermal

probe system, it can be used to fill the circuits:

1) Close the shut-off valves in the direction of the heat pump.

2) Connect the fill pipe to the fill valve hose connection and the

drain pipe to the deaerator - dirt separator hose connection. If

it is filled with a mixture of water and glycol, or with saline

solutions, place a container at the edge of the drain pipe to

stop any fluid from leaking into the environment.

3) The air vent fitted with hygroscopic safety cap releases air from

the system.

Do not tamper with the hygroscopic safety cap

which must be fully tightened to guarantee closure

of the valve and to prevent any potential damage

from water leakages.

Seal test

When all circuits have been filled, the system seal test can be

carried out.

1) Disconnect the drain pipe and close the corresponding drain

cock. Connect the test system pump to the fill pipe.

2) Bring the circuit up to pressure, to a maximum of 2,5 bar, for the

set period of time.

During the test, the
pressure

must

not

exceed 2,5 bar

Advertising