EVCO EPH4EXP Manuale d'uso
C-pro 3 exp hecto, I/o expansion

EVCO S.p.A. • Code 104CP3EHP0A113 • page 1/2
c-pro 3 EXP hecto+
I/O expansion
version 1.1
DIGITAL OUTPUTS
- digital outputs 1, 2, 3, 4 and 5 (electromechanical relays).
TERM. MEANING
CO1/2 common digital outputs 1 and 2
NO1
normally open contact digital output 1
NO2
normally open contact digital output 2
NO3
normally open contact digital output 3
CO3/4/5 common digital outputs 3, 4 and 5
CO3/4/5 common digital outputs 3, 4 and 5
NO4
normally open contact digital output 4
NO5
normally open contact digital output 5
- digital output 6 (electromechanical relay).
TERM. MEANING
CO6
common digital output 6
NO6
normally open contact digital output 6
NC6
normally closed contact digital output 6
ANALOG INPUTS / OUTPUTS
The analog input 4 is for NTC probes.
TERM. MEANING
AI4
analog input 4
AO1
analog output 1 (PWM signal)
GND
ground
AO2
analog output 2 (configurable via configuration parameter
for 0-20 mA / 4-20 mA / 0-10 V signal)
AO3
analog output 3 (configurable via configuration parameter
for 0-20 mA / 4-20 mA / 0-10 V signal)
The analog output 1 is usable on condition that the instrument is sup-
plied in alternate current and the phase supplying the instrument is the
same supplying the user driven by the output.
The analog output 1 and the analog output 2 are not independent
each other but they work in the same way.
DIGITAL INPUTS
TERM. MEANING
COM
common digital inputs
DI1
digital input 1
DI2
digital input 2
DI3
digital input 3
DI4
digital input 4
DI5
digital input 5
The digital inputs are usable on condition that they are supplied at
24 VAC / DC.
ANALOG INPUTS
The analog inputs 1, 2 and 3 are configurable via configuration param-
eter for PTC / NTC / Pt 1000 probes / 0-20 mA / 4-20 mA / 0-5 V ratiometric
/ 0-10 V transducers.
TERM. MEANING
AI1
analog input 1
AI2
analog input 2
AI3
analog input 3
GND
ground
+5V
power supply 0-5 V ratiometric transducers (5 VDC,
40 mA max.)
+24V
power supply 0-20 mA / 4-20 mA / 0-10 V transducers
(24 VDC, 120 mA max.)
PROG
Port to update the firmware of the instrument.
POWER SUPPLY
TERM. MEANING
V≅
power supply instrument (24 VAC / 20... 40 VDC)
V≅
power supply instrument (24 VAC / 20... 40 VDC)
If the instrument is supplied in direct current, one will not have to re-
spect the polarity of the power supply voltage.
5.2
Plugging in the termination of the CAN port
Position micro-switch 2 on position ON to plug in the termination of the
CAN port.
5.3
Additional information for electrical connection
• do not operate on the terminal blocks with electrical or pneumatic
screwers
• if the instrument has been moved from a cold location to a warm one,
the humidity could condense on the inside; wait about an hour be-
fore supplying it
• test the working power supply voltage, working electrical frequency
and working electrical power of the instrument; they must correspond
with the local power supply
• connect the instrument to the other devices using a twisted pair
• disconnect the local power supply before servicing the instrument
• do not use the instrument as safety device
• for repairs and information on the instrument please contact EVCO
sales network.
GB
ENGLISH
1
GETTING STARTED
1.1
Important
Read these instructions carefully before installing and using the instru-
ment and follow all additional information for installation and electrical
connection; keep these instructions close to the instrument for future
consultations.
The instrument must be disposed according to the local
legislation about the collection for electrical and electronic
equipment.
2
INTRODUCTION
2.1
Introduction
c-pro 3 EXP hecto+ is an I/O expansion.
The expansion is available in blind version and is usable for example
with a programmable controller such as
c-pro 3 hecto or c-pro 3
mega.
The instrument has got:
- 4 analog inputs of which 3 configurable via configuration parameter
for PTC / NTC / Pt 1000 probes / 0-20 mA / 4-20 mA / 0-5 V ratiometric
/ 0-10 V transducers and 1 for NTC probes
- 5 optoisolated digital inputs at 24 VAC / DC
- 3 analog outputs of which 1 non optoisolated PWM output and 2
non optoisolated outputs configurable via configuration parameter
for 0-20 mA / 4-20 mA / 0-10 V signal
- 6 digital outputs (electromechanical relays) of which five
3 res. A @ 250 VAC SPST outputs and one 5 res. A @ 250 VAC SPDT
output
- 2 non optoisolated communication ports of which 1 CAN port with
CANbus communication protocol and 1 port to update the firmware
of the instrument.
The device looks in case 4 DIN modules.
Installation is in electrical panel, on DIN rail.
For further information please consult the
Hardware manual of
c-pro 3.
3
DESCRIPTION
3.1
Description
The following table shows the meaning of the parts of the instrument.
PART
MEANING
1
micro-switch to plug in the termination of the CAN port
2
CAN port
3
digital outputs
4
analog outputs
5
analog inputs
6
port to update the firmware of the instrument
7
power supply
8
digital inputs
9
signalling LEDs
4
SIZE AND INSTALLATION
4.1
Size
4 DIN modules; size in mm (in).
4.2
Installation
On DIN rail 35.0 x 7.5 mm (1.377 x 0.295 in) or 35.0 x 15.0 mm
(1.377 x 0.590 in).
To install
c-pro 3 EXP hecto+ operate as shown in the following draw-
ing.
To remove
c-pro 3 EXP hecto+ remove possible extractable screw ter-
minal blocks plugged at the bottom first, then operate on the DIN rail
clips with a screwdriver as shown in the following drawing.
To install
c-pro 3 EXP hecto+ again press the DIN rail clips to the end
first.
4.3
Additional information for installation
• working conditions (working temperature, humidity, etc.) must be be-
tween the limits indicated in the technical data
• do not install the instrument close to heating sources (heaters, hot air
ducts, etc.), devices provided with big magnetos (big speakers, etc.),
locations subject to direct sunlight, rain, humidity, dust, mechanical
vibrations or bumps
• according to the safety legislation, the protection against electrical
parts must be ensured by a correct installation of the instrument; the
parts that ensure the protection must be installed so that you can not
remove them if not by using a tool.
5
ELECTRICAL CONNECTION
5.1
Electrical connection
The following tables show the meaning of the connectors.
MICRO-SWITCH
Micro-switch to plug in the termination of the CAN port; also look at
paragraph 5.2.
CAN BUS
CAN port.
TERM. MEANING
CAN + signal +
CAN -
signal -
GND
ground
6
SIGNALS
6.1
LEDs at the front of the instrument
LED
MEANING
ON
LED power supply
if it is lit, the instrument will be supplied
if it is out, the instrument will not be supplied
RUN
LED run
if it is lit, the application software will be compiled and run-
ning in release modality
LED system alarm
if it is lit, an alarm system not resettable via software will be
running
if it flashes slowly, a system alarm with automatic reset will
be running
if it flashes quickly, a system alarm with manual reset will be
running
if it is out, no alarm system will be running
CAN
LED CANbus communication
if it is lit, the instrument will be configured to communicate
via CANbus with another device but the CAN communica-
tion will not have been set up
if it flashes slowly, the CANbus communication will have been
set up but it will not be completely correct
if it flashes quickly, the CANbus communication will have
been set up and will be correct
if it is out, no CANbus communication will be running
L1
LED not used
7
TECHNICAL DATA
7.1
Technical data
Purpose of control: programmable controller for applications in re-
frigeration, ventilation and air conditioning.
Construction of control: electronic control device to be incorpo-
rated.
Box: self-extinguishing grey.
Size: 71.0 x 128.0 x 60.0 mm (2.795 x 5.039 x 2.362 in); 4 DIN mod-
ules.
Size refers to the instrument with all the connectors properly plugged.
Installation: on DIN rail 35.0 x 7.5 mm (1.377 x 0.295 in) or
35.0 x 15.0 mm (1.377 x 0.590 in).
Index of protection: IP20; IP40 the front.
Connections: male extractable screw terminal blocks pitch 5.0 mm
(0.196 in; power supply, inputs, outputs and CAN port) for conductors
up to 2.5 mm² (0.0038 in²), 6 poles female telephone connector (port
to update the firmware of the instrument).
The maximum lengths of the connecting cables are the followings:
• power supply instrument: 30 m (98 ft)
• analog inputs: 100 m (328 ft)
• power supply transducers: 100 m (328 ft)
• digital inputs: 100 m (328 ft)
• PWM analog output: 1 m (3.280 ft)
• 0-20 mA / 4-20 mA / 0-10 V analog outputs: 30 m (98 ft)
• digital outputs (electromechanical relays): 100 m (328 ft)
• CAN port:
- 1,000 m (3,280 ft) with baud rate 20,000 baud
- 500 m (1,640 ft) with baud rate 50,000 baud
- 250 m (820 ft) with baud rate 125,000 baud
- 50 m (164 ft) with baud rate 500,000 baud.
One suggests using the connecting kit CJAV15 (female extractable screw
terminal blocks pitch 5.0 mm, 0.196 in; to order separately).
Working temperature: from -20 to 55 °C (-4 to 131 °F).
Working humidity: from 5 to 95% of relative humidity without con-
densate.
Pollution situation: 2.
Power supply: 24 VAC, 50 / 60 Hz, 30 VA max. or 20... 40 VDC,
22 W max, supplied from a class 2 circuit.
Protect the power supply with a fuse rated 0.8A-T 250 V.
Overvoltage category: III.
Analog inputs: 4 inputs, of which 3 configurable via configuration
parameter for PTC / NTC / Pt 1000 probes / 0-20 mA / 4-20 mA / 0-5 V
ratiometric / 0-10 V transducers and 1 for NTC probes.
Power supply 0-5 V ratiometric transducers: 5 VDC, 40 mA max.
Power supply 0-20 mA / 4-20 mA / 0-10 V transducers: 24 VDC, 120 mA
max.
Working range: from -50 to 150 °C (-58 to 302 °F) for PTC probe,
from -50 to 120 °C (-58 to 248 °F) for NTC probe, from -100 to 400 °C
(-148 to 752 °F) for Pt 1000 probe.
Digital inputs: 5 optoisolated inputs at 24 VAC / DC.
Resolution: 0.1 °C for PTC / NTC probes, 0.1 °C for Pt 1000 probes,
0.01 mA for 0-20 mA / 4-20 mA transducers, 0.01 V for 0-10 V transduc-
ers.
Analog outputs: 3 outputs:
• 1 non optoisolated PWM output
• 2 non optoisolated outputs configurable via configuration parameter
for 0-20 mA / 4-20 mA / 0-10 V signal.
Power supply driving the PWM analog output: 24 VDC, 50 mA max.
Digital outputs: 6 outputs (electromechanical relays):
• five 3 res. A @ 250 VAC SPST outputs (K1, K2, K3, K4 and K5)
• one 5 res. A @ 250 VAC SPDT output (K6).
Type of actions and additional features: 1B.
Communication ports: 2 non optoisolated ports:
• 1 CAN port with CANbus communication protocol
• 1 port to update the firmware of the instrument.
I
ITALIANO
1
IMPORTANTE
1.1
Importante
Leggere attentamente queste istruzioni prima dell’installazione e prima
dell’uso e seguire tutte le avvertenze per l’installazione e per il collega-
mento elettrico; conservare queste istruzioni con lo strumento per con-
sultazioni future.
Lo strumento deve essere smaltito secondo le normative
locali in merito alla raccolta delle apparecchiature elettriche
ed elettroniche.
2
INTRODUZIONE
2.1
Introduzione
c-pro 3 EXP hecto+ è un’espansione di I/O.
L’espansione è disponibile in versione cieca ed è utilizzabile per esempio
con un controllore programmabile come
c-pro 3 hecto o c-pro 3
mega.
Lo strumento dispone di:
- 4 ingressi analogici di cui 3 configurabili via parametro di configura-
zione per sonde PTC / NTC / Pt 1000 / trasduttori 0-20 mA / 4-20 mA
/ 0-5 V raziometrici / 0-10 V e 1 per sonde NTC
- 5 ingressi digitali optoisolati a 24 VAC / DC
- 3 uscite analogiche di cui 1 non optoisolata di tipo PWM e 2 non
optoisolate configurabili via parametro di configurazione per segnale
di tipo 0-20 mA / 4-20 mA / 0-10 V
- 6 uscite digitali (relè elettromeccanici) di cui 5 da 3 A res. @ 250 VAC di
tipo SPST e 1 da 5 A res. @ 250 VAC di tipo SPDT
- 2 porte di comunicazione non optoisolate di cui 1 di tipo CAN con
protocollo di comunicazione CANbus e 1 per l’aggiornamento del
firmware dello strumento.
Il dispositivo si presenta in contenitore 4 moduli DIN.
L'installazione è prevista in un quadro elettrico, su guida DIN.
Per ulteriori informazioni consultare il
Manuale hardware di c-pro 3.
3
DESCRIZIONE
3.1
Descrizione
La seguente tabella illustra il significato delle parti dello strumento.
PARTE SIGNIFICATO
1
micro-switch per inserire la terminazione della porta CAN
2
porta CAN
3
uscite digitali
4
uscite analogiche
5
ingressi analogici
6
porta per l’aggiornamento del firmware dello strumento
7
alimentazione
8
ingressi digitali
9
LED di segnalazione
4
DIMENSIONI E INSTALLAZIONE
4.1
Dimensioni
4 moduli DIN; le dimensioni sono espresse in mm (in).
4.2
Installazione
Su guida DIN 35,0 x 7,5 mm (1,377 x 0,295 in) o 35,0 x 15,0 mm
(1,377 x 0,590 in).
Per installare
c-pro 3 EXP hecto+ operare come indicato nel seguente
disegno.
Per rimuovere
c-pro 3 EXP hecto+ rimuovere prima eventuali morsettiere
a vite estraibili inserite nella parte bassa, quindi operare sulla clip della
guida DIN con un cacciavite come indicato nel seguente disegno.
Per installare nuovamente
c-pro 3 EXP hecto+ premere prima a fondo
la clip della guida DIN.
4.3
Avvertenze per l’installazione
• accertarsi che le condizioni di lavoro (temperatura di impiego, umidi-
tà, ecc.) rientrino nei limiti indicati nei dati tecnici
• non installare lo strumento in prossimità di fonti di calore (resistenze,
condotti dell’aria calda, ecc.), di apparecchi con forti magneti (grossi
diffusori, ecc.), di luoghi soggetti alla luce solare diretta, pioggia, umi-
dità, polvere eccessiva, vibrazioni meccaniche o scosse
• in conformità alle normative sulla sicurezza, la protezione contro even-
tuali contatti con le parti elettriche deve essere assicurata mediante
una corretta installazione dello strumento; tutte le parti che assicurano
la protezione devono essere fissate in modo tale da non poter essere
rimosse senza l’aiuto di un utensile.