36

6 - START UP

1.

Tap

2.

Hot water outlet button

3.

Hot water outlet switch

4.

Machine on indicator

5.

Gas on/off valve

6.

Main switch

7.

Right vaporiser tap

8.

Left vaporiser tap

9.

Cup-warmer switch

10.

Boiler/pump pressure gauge

11.

Optional cappuccino maker

12.

Boiler level indicator

13.

Left vaporiser tap

14.

Right vaporiser tap

15.

Hot water outlet pipe

16.

Unit D control keyboard

17.

Unit E control keyboard

18.

Optional dose-counter display

19.

E delivery indicator

20.

D delivery led

Once the water, gas and electrical connections have been made,
proceed to start up the machine.

Open the mains water supply tap (A).
Close the protection switch (D)

Position the machine main switch (8) to position the machine
on indicator will come on (3).

The auto-levelling device will come into operation so that the water
reaches a normal level in the boiler (12).

Position the main switch (6) to position for operation at normal
power or to position for operation at full power, thereby
powering the resistances.

Wait for the pressure to reach its operational pressure 1.1

÷1.3 atm

checking the boiler pressure on the gauge (10).

Should the machine fail to stabilize on the indicated values it is
necessary to calibrate the pressure switch as described in
paragraph 6.2.

In the event of a machine featuring a gas heating system, it is
necessary to switch on the gas by operating the gas valve (4) after
operating the main switch (6), keeping the piezoelectric switch
pressed (5) until the gas remains on.

Then check the pressure on the pump gauge (10) putting a unit
into operation with filter holder engaged filled with ground, dosed
and pressed coffee in order to achieve an effective working pressure
of 8/9 atm.
Should re-calibration of the pump pressure be necessary this
operation should be undertaken as indicated in paragraph 6.3.

The machine is now ready for use.

6.1

LONG COFFEE GIGLEUR

The machine is fitted with a gigleur ( 1 per unit) with a clearance of
0.6 mm (Cod.26G0074/01).

For greater coffee delivery speed, in the case of long coffees, no.2
gigleurs are also included with the machine (complete with seals)
with a clearance of 0.8 mm (Cod.26G0073/01).

The gigleur is located in the exchanger supply fitting (1 per group).

IMPORTANT
Do not press the hot water delivery switch or button (2)
before the correct working temperature of 1.1 atm is
reached, as indicated on the boiler gauge (10).

Fig.6.01